Industrial Equipment Sales Agreements in Ontario: Acceptance Testing, Installation and Final Payment
Updated: 2 days ago
You deliver a $400,000 packaging machine. The buyer’s electrical work is incomplete, so your technician can’t commission it. The contract ties the last 20% to “successful installation and acceptance,” but it gives the buyer no deadline to prepare the site or run the test. The machine is on the customer’s floor, your technician needs to come back, and $80,000 remains outstanding.
An industrial equipment sales agreement in Ontario should define what the supplier will deliver, what the buyer must have ready, and what triggers each payment. Delivery, installation, commissioning and acceptance may happen weeks apart. Before signing, decide what each milestone means and who bears the cost if it’s delayed.

In this article
1. What an Industrial Equipment Sales Agreement in Ontario Should Say About Installation
List the equipment, options and services included in the price. Does installation cover unloading, rigging and anchoring, or does the buyer arrange those separately? Does commissioning include connecting to the buyer’s production line, integrating controls, running trial product or training operators? If your quote assumes the buyer will supply a contractor or handle part of the work, carry that assumption into the signed agreement.
Name who can approve work outside the original scope and how that affects fees and timing. For example, if a site layout change requires a second installation visit, the technician should know who can authorize the return trip and how travel and labour will be billed.
2. Make Site Readiness a Condition of Scheduling
Put the site requirements in a schedule both teams can use. Depending on the machine, that may include electrical service, compressed air, floor capacity, access for unloading, network connections and test materials. Identify who confirms readiness and when the supplier can rely on that confirmation.
Address what happens if the site isn’t ready. Can the supplier postpone shipment or charge for storage, standby time or a return visit? Does a buyer-caused delay affect any payment milestone? Agree on those consequences before the supplier books technicians or ships the machine.
Agree on the cost of an unready site before the technician is booked, not after.
3. Agree on What Counts as a Passed Acceptance Test
Decide whether you’ll test the machine at the factory before shipment, at the buyer’s site after installation, or both. A factory acceptance test might verify the machine’s basic functions. A site acceptance test might check how it performs with the buyer’s product, operators and upstream equipment. Define what each test is meant to prove.
Specify the test materials, run duration, performance thresholds and who records the results. “Runs at 60 units per minute” needs context: which product, for how long, and with what tolerance for rejects? Set a deadline for the buyer to report failures and a process for correction and retesting. Distinguish a failure that prevents acceptance from a minor item the supplier can fix after sign-off.
Negotiating an equipment sale? Book a consultation and we will help you set acceptance tests, site readiness terms and payment milestones that hold up.
4. Tie Final Payment to a Milestone Both Sides Can Verify
Split the price across milestones that reflect when costs are incurred and work is completed. If the final instalment depends on acceptance, say what evidence triggers the invoice and how long the buyer has to sign off or give specific reasons for rejecting the test results.
Address delays the supplier cannot resolve. If the machine is ready but the buyer can’t provide the agreed test materials, the parties might agree that part of the balance becomes due after a defined delay while preserving the buyer’s right to complete testing later. Sections 33 and 34 of Ontario’s Sale of Goods Act address the buyer’s opportunity to examine goods and when goods are deemed accepted. A written test and payment schedule helps the parties agree in advance on how those steps will work for this machine.
5. Keep Acceptance, Warranty and Delivery Risk Separate
Confirm when the warranty starts and what it covers. If commissioning is delayed for months after delivery, the parties may have different expectations about when coverage begins. If the buyer starts using the machine commercially before formal sign-off, specify what that means for acceptance, payment and warranty. Address trial use separately so the buyer can run agreed tests without creating uncertainty about whether the machine has been accepted.
Also specify when risk of loss passes and who insures the equipment in transit, in storage and during installation. A machine can be delivered and still be awaiting acceptance. The contract should tell both sides who bears the cost if it’s damaged in that interval.
A machine can be delivered and still be awaiting acceptance. The contract should say who carries the risk in between.
Frequently Asked Questions
When is industrial equipment considered accepted under Ontario law?
Under section 34 of Ontario’s Sale of Goods Act, a buyer is deemed to accept goods when it tells the seller it accepts them, acts in a way inconsistent with the seller’s ownership after delivery, or keeps them beyond a reasonable time without rejecting them. Your agreement can set a clearer, test-based acceptance process, which is why written acceptance criteria matter.
Does the buyer get to inspect the machine before accepting it?
Yes. Under section 33 of the Sale of Goods Act, a buyer who has not previously examined the goods is not deemed to accept them until it has had a reasonable opportunity to examine them. Your agreement should define what testing counts as that examination and how long the buyer has to complete it.
Who bears the risk of loss while the equipment awaits acceptance?
Unless the parties agree otherwise, section 21 of the Sale of Goods Act places risk with whoever owns the goods, whether or not they have been delivered, and a party whose fault delays delivery bears the resulting loss. Your contract should state who insures the machine in transit, in storage and during installation.
What if the buyer’s site is not ready for installation?
The agreement should say whether the supplier can postpone shipment, charge for storage, standby time or a return visit, and whether a buyer-caused delay affects any payment milestone. Agree on these consequences before technicians are booked.
When should the equipment warranty start?
Choose a start date explicitly, such as shipment, commissioning or acceptance, and say what happens if the buyer uses the machine commercially before sign-off. Delta Law drafts warranty, acceptance and payment terms that work together, for a flat fee agreed in advance.
Learn More
To see how we support industrial equipment and machinery businesses, visit our Legal Services for Industrial Equipment & Machinery page, or explore our Legal Services for Manufacturers & Distributors.
Need an Industrial Equipment Sales Agreement in Ontario?
Installation scope, site readiness, acceptance testing and final payment all need to be settled before the machine ships. Delta Law helps Ontario equipment manufacturers and suppliers draft and negotiate these agreements.
This article provides general information only and is not legal advice. Reading it does not create a lawyer-client relationship.